How to calculate concrete for a foundation
What this calculator does
You enter the outside size of the house and the strip width and height. The calculator shows how many cubic metres of concrete you need, how long the strip is along its centreline and what its cross-section is. Add the mixer volume and it tells you how many loads to order.
Step-by-step example
A 10 × 8 m house with a strip 0.4 m wide. The outside perimeter is 36 m, but a strip is measured along its centreline, so four strip widths come off it: 36 − 1.6 = 34.4 m. The cross-section is 0.4 × 1.5 = 0.6 m². Total 34.4 × 0.6 = 20.64 m³. With a 6 m inner strip it is 24.24 m³, which is four loads from a 7 m³ mixer.
Why the centreline, not the perimeter
At the corners two strips overlap. If you measure the outside perimeter, each corner is counted twice. In the example above that is almost a cubic metre of extra concrete. The centreline runs through the middle of the strip, so each corner is counted exactly once.
Inner strips
Load-bearing inner walls also stand on a strip. Add up their length and enter it as one number. The calculator uses the same width and height as for the outer strips: if an inner strip is narrower, calculate it separately.
Extra
The Extra field adds a percentage to the volume. You need it because some concrete stays in the mixer and on the chute, and formwork is never perfectly straight. Leave it empty for no extra.
What is not included
The calculator covers only the strip concrete. The sand or gravel bed, rebar, formwork and waterproofing are separate materials with their own calculations.
Common questions about foundations
What height should I enter?
The full strip height: the part below ground plus the plinth above it. This is the height you set the formwork to.
Why are there more mixer loads than volume divided by mixer size?
Loads are whole numbers and are rounded up. 24.24 m³ at 7 m³ a load is four loads, because the last one goes out part-full. You can agree on a part load, but you usually pay for a full one.
Can I use this for a slab or piers?
No, this calculator is for strips only. For a slab the volume is area times thickness, for piers it is cross-section times height times the number of piers.
How much cement is in this concrete?
The calculator does not break that down. Ready-mix concrete is ordered by the cubic metre and by grade, not by cement: the grade and the mix are a question for the plant.